The VPSA-4000-80 oxygen production project of a certain group in Shandong Province has been successfully put into operation.

发布时间:2025-07-23 17:44

作者:

来源:


 

On June 21, 2025, the VPSA-4000Nm³/h-80% purity oxygen generation unit undertaken by our company for a certain group company in Weihai, Shandong Province, was successfully put into operation.

Oxygen buffer tank in place

Adsorption tower in place

Dual-shaft motor hoisting

Adsorption tower hoisting

This oxygen generation project started on May 24, 2025, with our company's construction personnel entering the site. It took only 29 days to successfully produce oxygen, while meeting the design indicators: oxygen purity of 80.5%, oxygen flow rate of 4508Nm³/h, and oxygen production active power consumption ≤0.3KWh/Nm³ (equivalent to 100% pure oxygen), etc. The performance parameters have received unanimous praise from the owner.
This VPSA-4000-80 oxygen generation unit is an old plant renovation project, which presented many challenges to the construction: large and heavy equipment could only be air-dropped from the top of the more than 30-meter-high plant; the owner's oxygen demand was urgent, and the construction period was very tight; there was no crane in the plant, increasing the use of cranes during equipment installation and piping.

Overall view of the adsorption tower

 

In response to these construction difficulties, the construction personnel reasonably arranged the construction, overcame difficulties, and worked overtime and shift work. During the molecular sieve filling, 24-hour construction was implemented, ensuring continuous operation even when personnel rested, securing valuable construction time. Despite all difficulties, the owner's requirements for progress, quality, and safety were met, enabling the project to be successfully put into operation.

All indicators meet the standards

User training

Successful commissioning and ribbon-cutting ceremony

User inspection of oxygen generation unit production

Related recommend


The VPSA-4000-80 oxygen production project of a certain group in Shandong Province has been successfully put into operation.

On June 21, 2025, the VPSA-4000Nm³/h-80% purity oxygen production unit undertaken by our company for a certain group company in Weihai, Shandong Province was successfully put into operation.

2025-07-23 17:44